不中断交通条件下大跨度跨铁路连续梁支座更换设计与施工——以广州某大跨度跨铁路连续梁桥支座更换为例
DOI:
作者:
作者单位:

作者简介:

通讯作者:

基金项目:


Design and Construction of Continuous Beam Supports Replacement for Long Span Railway under Continuous Traffic Conditions:Taking the Replacement of the Support of a Long-span Railway Continuous Beam Bridge in Guangzhou as an Example
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
    摘要:

    既有桥梁在运营一定时间后经常出现各种支座病害,严重影响桥梁的正常使用。以广州某大跨度跨铁路连续梁桥支座更换为背景,研究满足铁路临近营业线施工的分幅分步顶升方案。根据设计顶升方案运用有限元软件 Midas Civil 进行计算分析,考虑不中断交通工况,计算得出各个支座的支座反力及顶升3 mm高度状态下桥梁结构的受力状态,为顶升施工提供理论依据。同时合理布置千斤顶数量,为大吨位的顶升施工积累经验,为同类型桥梁的支座更换提供借鉴。

    Abstract:

    The existing prestressed concrete continuous box girder bridge often has various bearing diseases after a certain period of operation, which seriously affects the normal use of the bridge. Taking the replacement of the support of a large-span railway continuous beam bridge in Guangzhou as the background, a segmented and step-by-step lifting scheme is adopted to meet the construction requirements of the railway near the business line. According to the design of the lifting plan, finite element software Midas Civil was used for calculation and analysis. Considering uninterrupted traffic conditions, the support reaction forces of each support and the stress state of the bridge structure under the lifting height of 3mm were calculated, providing a theoretical basis for lifting construction. At the same time, the number of jacks should be reasonably arranged to accumulate experience for large-tonnage lifting construction and provide reference for the replacement of bearings for similar bridges in the future.

    参考文献
    相似文献
    引证文献
引用本文

周界龙,李智鹏,肖啸,王文哲.不中断交通条件下大跨度跨铁路连续梁支座更换设计与施工——以广州某大跨度跨铁路连续梁桥支座更换为例[J].科技与产业,2024,24(19):296-303