浅埋软岩大断面隧道施工工法研究——以滨江路隧道工程为例
DOI:
作者:
作者单位:

作者简介:

通讯作者:

基金项目:


Research on the Construction Methods for Deep Buried Soft Rock Large-diameter Tunnels:A Case Study of the Bin Jiang Load Tunnel Project
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
    摘要:

    为了研究比选出浅埋软岩大断面隧道最优的开挖工法,建立了台阶法、交叉中隔壁法和双侧壁导坑法的施工精细化数值模型,对浅埋软岩大断面隧道施工过程中地层位移场的时空演化规律、支护结构应力分布情况进行研究。结果表明:双侧壁导坑法开挖引起的拱顶下沉位移较小;三种工法开挖引起的地表沉降均为U形,双侧壁导坑法地表沉降位移最小;双侧壁导坑法计算得到的初期支护应力较高,但处于安全范围内。

    Abstract:

    To study the optimal excavation method for shallow-buried soft rock large-section tunnels, detailed numerical models were established for the step method, the cross-middle wall method and the double side wall guiding pit method. The research focused on the time-space evolution of the ground displacement field during the construction process and the stress distribution of the supporting structure. The results show than the excavation using the double side wall guiding pit method induces smaller crown settlement displacements. The ground settlement caused by the three excavation methods is characterized by a U-shaped curve, with the double side wall guiding pit method resulting in the smallest surface settlement displacement. The initial support stress calculated for the double side wall guiding pit method is higher, but remains within a safe range.

    参考文献
    相似文献
    引证文献
引用本文

索华志,毛兴吉,黎国强.浅埋软岩大断面隧道施工工法研究——以滨江路隧道工程为例[J].科技和产业,2025,25(10):25-31

复制
文章指标
  • 点击次数:
  • 下载次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2025-06-06
×
关于“低空经济”“人工智能与产业融合”专栏征稿的通知